Inspired by our friends who started a blog about their timeline of build I am going to do the same. I will update it as things change:

19/9/2015 – Land Deposit Paid

13/2/2016 – Display Home Walkthrough with Sales Consultant

12/3/2016 – Paid Initial Deposit

4/7/2016 – World of Style Appointment 1

5/7/2016 – World of style Appointment 2

21/7/2016 – Tender Appointment

17/8/2016 – Contract Appointment

27/9/2016 – Land Titled

14/10/2016 – Developer approval lodged

7/11/16 – Developer changes received

10/1/17 – Received Developer Approval

3/3/17 – Received Council Approval

6/3/17 – Received Building Permit

21/3/17 – Site cut

30/3/17 – Piers in

5/4/17 – Pre pour inspection with Darbecca

6/4/17 – Slab pour

18/5/17 – Frame inspection with Darbecca

28/6/17 – Pre-Plaster inspection with Darbecca

Advertisements

4 thoughts on “Timeline

  1. Hi, I love your house selections and the overall look you have gone with design wise, I’m sure you will have a beautiful home when it’s all finished. I am also building a Porter Davis house, and have decided on Timeless Grey for the render colour. Would you be able to please tell me the colour you have selected for the downpipes? Thanks.

    Like

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s